[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-898593":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},898593,582,1,"单选题","关于工程量清单中的计日工，下列说法中正确的是（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","即指零星工作所消耗的人工工时",false,{"key":16,"text":17,"correct":14},"B","在投标时计入总价，其数量和单价由投标人填报",{"key":19,"text":20,"correct":14},"C","应按投标文件载明的数量和单价进行结算",{"key":22,"text":23,"correct":24},"D","在编制招标工程量清单时，暂定数量由招标人填写",true,"2020版教材P51 计日工表的项目名称、暂定数量由招标人填写，编制招标控制价时，单价由招标人按有关计价规定确定；投标时，单价由投标人自主报价，按暂定数量计算合价计入投标总价中。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程计价","建筑工程",0]