[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-898591":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},898591,582,1,"单选题","根据《建设工程工程量清单计价规范》GB50500-2013的规定，在合同约定之外的或者因变更而产生的、工程量清单中没有相应的项目的额外工作，尤其是那些难以事先商定价格的额外工作，应计列入（ ）之中。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","暂列金额",false,{"key":16,"text":17,"correct":14},"B","暂估价",{"key":19,"text":20,"correct":21},"C","计日工",true,{"key":23,"text":24,"correct":14},"D","总承包服务费","2020版教材P50 计日工是为了解决现场发生的零星工作的计价而设立的。计日工适用的所谓零星项目或工作一般是指合同约定之外的或者因变更而产生的、工程量清单中没有相应项目的额外工作，尤其是那些难以事先商定价格的额外工作。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程计价","建筑工程",0]