[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-898581":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},898581,582,1,"单选题","根据《建设工程工程量清单计价规范》GB 50500-2013，关于计日工，下列说法中正确的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","计日工表包括各种人工，不应包括材料、施工机械",false,{"key":16,"text":17,"correct":18},"B","计日工按综合单价计价，投标时应计入投标总价",true,{"key":20,"text":21,"correct":14},"C","计日工表中的项目名称由招标人填写，工程数量由投标人填写",{"key":23,"text":24,"correct":14},"D","计日工单价由投标人自主确定，并按计日工表中所列数量结算","2020版教材P50 计日工对完成零星工作所消耗的人工工日、材料数量、施工机具台班进行计量，并按照计日工表中填报的适用项目的单价进行计价支付。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程计价","建筑工程",0]