[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-898577":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},898577,582,1,"单选题","某分部分项工程的清单编码为010302006004，则该分部分项工程的清单项目顺序编码为（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","01",false,{"key":16,"text":17,"correct":14},"B","02",{"key":19,"text":20,"correct":14},"C","006",{"key":22,"text":23,"correct":24},"D","004",true,"2020版教材P44 根据工程量清单计价规范，项目编码以五级编码设置，从前往后依次为专业工程代码、附录分类顺序码、分部工程顺序码、分项工程顺序码和工程量清单项目名称顺序码。因此分部分项工程的清单顺序码为最后一级编码。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程计价","建筑工程",0]