[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-898575":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},898575,582,1,"单选题","有关其他项目清单的表述，下列内容中正确的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","暂列金额能保证合同结算价格不会超过合同价格",false,{"key":16,"text":17,"correct":18},"B","投标人应将材料暂估单价计入工程量清单综合单价报价中",true,{"key":20,"text":21,"correct":14},"C","专业工程的暂估价一般应是综合暂估价，应当包括管理费、利润、规费、税金在内",{"key":23,"text":24,"correct":14},"D","计日工适用的所谓零星工作一般是指合同约定之内的因变更而产生的额外工作","2020版教材P49 选项A错误，暂列金额是为了不可避免的价格调整而设立的；选项C错误，专业工程的暂估价一般应是综合暂估价，应当包括除规费、税金外的管理费、利润等取费；选项D错误，计日工适用的所谓零星工作一般是指合同约定之外的因变更而产生的额外工作。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程计价","建筑工程",0]