[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-898567":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},898567,582,1,"单选题","工程量清单计价的基础公式正确的是（ ）",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","分部分项工程费=∑（分部分项工程量×相应分部分项综合单价）",true,{"key":16,"text":17,"correct":18},"B","其他项目费=暂估价+计日工+总承包服务费",false,{"key":20,"text":21,"correct":18},"C","单位工程报价=分部分项工程费+措施项目费+其他项目费+规费",{"key":23,"text":24,"correct":18},"D","建设项目总报价=∑单位工程报价","2020版教材P39 其他项目费=暂列金额+暂估价+计日工+总承包服务费；单位工程报价=分部分项工程费+措施项目费+其他项目费+规费+税金；建设项目总报价=∑单项工程报价。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程计价","建筑工程",0]