[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-898556":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},898556,582,1,"单选题","工程定额是对有关消耗量的数量规定，这种数量关系没有体现出（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","正常的施工条件",false,{"key":16,"text":17,"correct":14},"B","合理的施工组织设计",{"key":19,"text":20,"correct":14},"C","生产要素消耗水平",{"key":22,"text":23,"correct":24},"D","一定时期的物价平均水平",true,"2020版教材P39 工程定额是指在正常施工条件下完成规定计量单位的合格建筑安装工程所消耗的人工、材料、施工机具台班、工期天数及相关费率等的数量标准，因此没有价格",{"id":6,"name":27,"category":28,"favorite":29},"建设工程计价","建筑工程",0]