[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-898554":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},898554,582,1,"单选题","下列定额中，项目划分最细的计价定额是（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","材料消耗定额",false,{"key":16,"text":17,"correct":14},"B","劳动定额",{"key":19,"text":20,"correct":21},"C","预算定额",true,{"key":23,"text":24,"correct":14},"D","概算定额","2020版教材P40 材料和劳动定额是数量标准，概算定额的项目划分粗细，与扩大初步设计的深度相适应，一般是在预算定额的基础上综合扩大而成的，每一扩大分项概算定额都包含了数项预算定额。@##",{"id":6,"name":27,"category":28,"favorite":29},"建设工程计价","建筑工程",0]