[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-898552":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},898552,582,1,"单选题","国外建筑工程造价构成中，（ ）用于在估算达到了一定的完整性并符合技术标准的基础上，由于物质、社会和经济的变化，导致估算增加的情况。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","直接建设成本",false,{"key":16,"text":17,"correct":14},"B","建设成本上升费",{"key":19,"text":20,"correct":21},"C","不可预见准备金",true,{"key":23,"text":24,"correct":14},"D","未明确项目准备金","本题考查的是国外建设工程造价构成。不可预见准备金（在未明确项目准备金之外）用于在估算达到了一定的完整性并符合技术标准的基础上，由于物质、社会和经济的变化，导致估算增加的情况。2020教材P2-4。@##",{"id":6,"name":27,"category":28,"favorite":29},"建设工程计价","建筑工程",0]