[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-898538":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},898538,582,1,"单选题","关于我国现行建设项目投资构成的说法中，正确的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","固定资产投资为建设投资和建设期利息之和",true,{"key":16,"text":17,"correct":18},"B","工程费用为直接费、间接费、利润和税金之和",false,{"key":20,"text":21,"correct":18},"C","生产性建设项目总投资为建设投资和建设期利息之和",{"key":23,"text":24,"correct":18},"D","工程造价为工程费用、工程建设其他费用和预备费之和","2020版教材P1 生产性建设项目总投资为建设投资、建设期利息和流动资金三部分。 工程造价与固定资产投资在量上相等，等于建设投资和建设期利息之和。工程费用是指直接构成固定资产实体的各种费用，可以分为建筑安装工程费和设备及工器具购置费。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程计价","建筑工程",0]