[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-898537":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},898537,582,1,"单选题","在世界银行工程造价的构成中，有一项费用有可能发生，有可能不发生，在正常建设条件下可能不动用，只是一种贮备。此项费用是（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","建设成本上升费用",false,{"key":16,"text":17,"correct":14},"B","项目间接建设成本",{"key":19,"text":20,"correct":14},"C","未明确项目准备金",{"key":22,"text":23,"correct":24},"D","不可预见准备金",true,"2020版教材P3 不可预见准备金只是一种储备、可能不动用。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程计价","建筑工程",0]