[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-898532":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},898532,582,1,"单选题","不可预见的地下障碍物处理的费用，应计入()。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","现场经费",false,{"key":16,"text":17,"correct":14},"B","施工企业管理费",{"key":19,"text":20,"correct":14},"C","价差预备费",{"key":22,"text":23,"correct":24},"D","基本预备费",true,"基本预备费一般由四个部分组成： 1)工程变更及洽商。 2)一般自然灾害处理。 3)不可预见的地下障碍物处理的费用。 4)超规超限设备运输增加的费用。 2020教材P30-31",{"id":6,"name":27,"category":28,"favorite":29},"建设工程计价","建筑工程",0]