[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-898520":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},898520,582,1,"单选题","一般自然灾害造成的损失和预防自然灾害所采取的措施费用，应计入（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","现场经费",false,{"key":16,"text":17,"correct":14},"B","施工企业管理费",{"key":19,"text":20,"correct":14},"C","价差预备费",{"key":22,"text":23,"correct":24},"D","基本预备费",true,"2020版教材P30 基本预备费一般由以下四部分构成：（1）工程变更及洽商。在批准的初步设计范围内，技术设计、施工图设计及施工过程'中所增加的工程费用；设计变更、工程变更、材料代用、局部地基处理等增加的费用。（2）—般自然灾害处理。一般自然灾害造成的损失和预防自然灾害所采取的措施费用。实行工程保险的工程项目，该费用应适当降低。（3）不可预见的地下障碍物处理的费用。（4）超规超限设备运输增加的费用。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程计价","建筑工程",0]