[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-898481":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},898481,582,1,"单选题","与一般计税方法相比，简易计税方法下计税基数的差异是()。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","税前造价",false,{"key":16,"text":17,"correct":14},"B","人工费、材料费、施工机具使用费、企业管理费、利润和规费之和",{"key":19,"text":20,"correct":14},"C","执行营业税改征增值税试点实施办法",{"key":22,"text":23,"correct":24},"D","各费用项目均以包含增值税进项税额的含税价格计算",true,"采用一般计税方法时，增值税的计税基数是税前造价，税前造价为人工费、材料费、施工机具使用费、企业管理费、利润和规费之和，各费用项目均以不包含增值税可抵扣进项税额的价格计算；当采用简易计税方法时，增值税的计税基数是税前造价，税前造价为人工费、材料费、施工机具使用费、企业管理费、利润和规费之和，各费用项目均以包含增值税进项税额的含税价格计算。2020教材P10-14",{"id":6,"name":27,"category":28,"favorite":29},"建设工程计价","建筑工程",0]