[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-898480":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},898480,582,1,"单选题","混凝土模板及支架(撑)费的计算方法通常是按照（ ）计算。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","按照混凝土构件的体积以m3",false,{"key":16,"text":17,"correct":14},"B","按照混凝土构件的长度以m",{"key":19,"text":20,"correct":14},"C","按照混凝土构件的截面面积以m2",{"key":22,"text":23,"correct":24},"D","按照模板与现浇混凝土构件的接触面积以m2",true,"本题考查的是按造价形成划分建筑安装工程费用项目构成和计算。混凝土模板及支架(撑)费通常按照模板与现浇混凝土构件的接触面积以m2计算。2020教材P15-20",{"id":6,"name":27,"category":28,"favorite":29},"建设工程计价","建筑工程",0]