[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-898408":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},898408,582,1,"单选题","某施工合同约定人工工资200 元\u002F工日，窝工补贴按人工工资的25%计算，在施工过程中发生了如下事件：①出现异常恶劣天气导致工程停工2 天，人员窝工20 个工日;②因恶劣天气导致场外道路中段，抢修道路用工20 个工日;③几天后，场外停电，停工1 天，人员窝工10 个工日。承包人可向发包人索赔的人工费为（ ）元、",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","1500",false,{"key":16,"text":17,"correct":14},"B","2500",{"key":19,"text":20,"correct":21},"C","4500",true,{"key":23,"text":24,"correct":14},"D","5500","各事件处理结果如下：（1）异常恶劣天气导致的停工通常不能进行费用索赔。（2）抢修道路用工的索赔额：20×200=4000（元）（3）停电导致的索赔额：10×200×25%=500（元）总索赔费用=4000+500=4500（元）",{"id":6,"name":27,"category":28,"favorite":29},"建设工程计价","建筑工程",0]