[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-898407":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},898407,582,1,"单选题","某施工合同约定采用价格指数及价格调整公式调整价格差额，调价因素及有关数据见下表。某月完成进度款为1500 万元，则该月应当支付给承包人的价格调整金额为（ ）万元。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","-30.3",false,{"key":16,"text":17,"correct":18},"B","36.45",true,{"key":20,"text":21,"correct":14},"C","112.5",{"key":23,"text":24,"correct":14},"D","130.5","P0=1500×{（0.3+[0.1×（90÷80）+0.1）×（102÷100）+0.15×（120÷110）+0.15×（110÷120）+0.20×（120÷115）]-1}=36.45 万元",{"id":6,"name":27,"category":28,"favorite":29},"建设工程计价","建筑工程",0]