[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-898406":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},898406,582,1,"单选题","某建筑工程钢筋综合用量1000t.施工合同中约定，结算时对钢筋综合价格涨幅±5%以上部分按造价处发布的基准价调整价格差额。承包人投标报价2400 元\u002Ft,投标期、施工期间造价管理机构发布的钢筋综合基准价格为2500 元\u002Ft、2800 元\u002Ft,则需增调钢筋材料费用为（ ）万元。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","17.5",true,{"key":16,"text":17,"correct":18},"B","28.0",false,{"key":20,"text":21,"correct":18},"C","30.0",{"key":23,"text":24,"correct":18},"D","40.0","本题考查的是物价变化类合同价款调整事项。（2800-2500×1.05）×1000=175000 元=17.5 万元。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程计价","建筑工程",0]