[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-898404":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},898404,582,1,"单选题","某分项工程招标工程量清单为4000 ㎡，施工中由于设计变更调减为3000 ㎡，该项目招标控制价综合单价为600 元\u002F㎡，投资报价为450\u002F元\u002F㎡。合同约定实际工程量与招标工程量偏差超过±15%时，综合单价以招标控制价位基础调整。若承包人报价浮动率为10%，该分享工程费结算价为（ ）万元。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","137.70",true,{"key":16,"text":17,"correct":18},"B","155.25",false,{"key":20,"text":21,"correct":18},"C","186.30",{"key":23,"text":24,"correct":18},"D","207.00s","3000÷4000=75%，工程量减少超过15%，需对单价调整。P2×（1-L）×（1-15%）=600×（1-10%）×（1-15%）=459（万元）P0\u003Cp2×（1-l）×（1-15%），450\u003C459，P1 按照P2×（1-L）×（1-15%）调整。结算价=459×3000=137.7（万元）",{"id":6,"name":27,"category":28,"favorite":29},"建设工程计价","建筑工程",0]