[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-898397":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},898397,582,1,"单选题","某挖土机挖土一次正常循环工作时间为50s，每次循环平均挖土量为0.5m3，机械正常利用系数为0.8，机械幅度差系数为25%，按8 小时工作制考虑，挖土方预算定额的机械台班消耗量为（ ）台班\u002F1000m3。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","5.43",true,{"key":16,"text":17,"correct":18},"B","7.2",false,{"key":20,"text":21,"correct":18},"C","8",{"key":23,"text":24,"correct":18},"D","8.68","本题考查预算定额中机械台班消耗量的计算。 预算定额机械耗用台班=施工定额机械耗用台班×（1+机械幅度差系数）， 机械纯工作1h 循环次数=3600\u002F50=72 次\u002F台时） 机械纯工作1h 正常生产率=72×0.5=36（m3\u002F小时） 施工机械台班产量定额=36×8×0.8=230.4（m3\u002F台班） 施工机械台班时间定额=1\u002F230.4=0.00434（台班\u002Fm3） 预算定额机械耗用台班=0.00434×（1+25%）=0.00543（台班\u002Fm3） 挖土方1000m3 的预算定额机械耗用台班量=1000×0.00543=5.43 台班）",{"id":6,"name":27,"category":28,"favorite":29},"建设工程计价","建筑工程",0]