[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-898395":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},898395,582,1,"单选题","已知某人工抹灰10 ㎡的基本工作时间为4 小时，辅助工作时间占工序作业时间的5%，准备与结束工作时间、不可避免的中断时回分部占工作日的6%、11%、3%。则该人工抹灰的时间定额为（ ）工日\u002F100 ㎡",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","6.3",false,{"key":16,"text":17,"correct":14},"B","6.56",{"key":19,"text":20,"correct":21},"C","6.58",true,{"key":23,"text":24,"correct":14},"D","6.67","",{"id":6,"name":27,"category":28,"favorite":29},"建设工程计价","建筑工程",0]