[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-898388":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},898388,582,1,"单选题","某工程进度计划网络图上的工作X（在关键线路上）与工作Y（在非关键线路上）同时受到异常恶劣气候条件的彩响，导致X 工作延误10 天，Y 工作延误15 天，该气候条件未对其他工作造成影晌，若Y工作的自由时差为20 天，则承包人可以向发包人索赔的工期是（ ）天。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","10",true,{"key":16,"text":17,"correct":18},"B","15",false,{"key":20,"text":21,"correct":18},"C","25",{"key":23,"text":24,"correct":18},"D","35","",{"id":6,"name":27,"category":28,"favorite":29},"建设工程计价","建筑工程",0]