[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-898386":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},898386,582,1,"单选题","对某招标工程进行报价分析，在不考虑安全文明施工费的前提下，承包人中标价为1500 万元，招标控制价为1600 万元，设计院编制的施工图预算为1550 万元，承包人认为的合理报价值为1540 万元，则承包人的报价浮动率是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","0.65%",false,{"key":16,"text":17,"correct":18},"B","6.25%",true,{"key":20,"text":21,"correct":14},"C","93.75%",{"key":23,"text":24,"correct":14},"D","96.25%","本题考查的是工程变更类合同价款调整事项。实行招标的工程：承包人报价浮动率=（1-中标价\u002F招标控制价）×100%=（1-1500\u002F1600）×100%=6.25%。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程计价","建筑工程",0]