[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-898379":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},898379,582,1,"单选题","某工程项目报告期需采购设备甲2 台，设备乙1 台。报告期、基期设备价格如下表所示，该工程报告期的设备价格指数为（ ）",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","1.00",false,{"key":16,"text":17,"correct":14},"B","1.13",{"key":19,"text":20,"correct":21},"C","1.20",true,{"key":23,"text":24,"correct":14},"D","1.40","设备价值指数=（2×35+1×50）\u002F（2×25+1×50）=1.20",{"id":6,"name":27,"category":28,"favorite":29},"建设工程计价","建筑工程",0]