[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-898372":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},898372,582,1,"单选题","通过计时观察，完成某工程的基本工时为6h\u002Fm3，辅助工作时间为工序作业时间的8%，规范时间占工作时间的15%，则完成该工程的时间定额是（ ）工日\u002Fm3。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","0.93",false,{"key":16,"text":17,"correct":14},"B","0.94",{"key":19,"text":20,"correct":14},"C","0.95",{"key":22,"text":23,"correct":24},"D","0.96",true,"6 小时=0.75（工日\u002Fm3）;工序作业时间=0.75\u002F（1-8%）=0.815;定额时间=0.815\u002F（1-15%）=0.96 工日\u002Fm3。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程计价","建筑工程",0]