[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-898368":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},898368,582,1,"单选题","某工业建设项目及其总装车间的建筑工程费、安装工程费、需安装设备费以及应摊入费用如下表所示，计算总装车间新增固定资产价值为（ ）万元。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","2521.50",false,{"key":16,"text":17,"correct":14},"B","2099.66",{"key":19,"text":20,"correct":14},"C","2098.66",{"key":22,"text":23,"correct":24},"D","2099.67",true,"新增固定资产价值的计算按照共同费用分摊方法： (1)一般情况下，建设单位管理费按建筑工程、安装工程、需安装设备价值总额等按比例分摊。(2)土地征用费、地质勘察和建筑工程设计费等费用则按建筑工程造价比例分摊。(3)生产工艺流程系统设计费按安装工程造价比例分摊。1000+350+670+120×（1000+350+670） ÷（5000+700+1500）+（130+100）×（1000÷5000）=1000+350+670+33.67+46=2099.67 万元。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程计价","建筑工程",0]