[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-898363":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},898363,582,1,"单选题","某建设工程项目关键线路上的A 工作由于非承包商的原因推迟了2 天，还有一个非关键线路上的B 工作也是由于非承包商的原因推迟了3 天，B 工作的总时差为4 天，则承包商可以索赔的工期是（ ）天。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","2",true,{"key":16,"text":17,"correct":18},"B","5",false,{"key":20,"text":21,"correct":18},"C","7",{"key":23,"text":24,"correct":18},"D","8","关键线路上的 A 工作由于非承包商的原因推迟了 2 天可以索赔。非关键线路上的 B 工作也是由于非承包商的原因推迟了 3 天，B 工作的总时差为 4 天，推迟的 3 天不会影响总工期，所以这 3 天不能索赔。承包商可以索赔的工期是 2 天。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程计价","建筑工程",0]