[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-898357":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},898357,582,1,"单选题","为了合理划分发承包双方的合同风险，施工合同中应当约定一个基准日。对于实行招标的建设工程，一般以（ ）前的第28 天作为基准日。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","投标截止时间",true,{"key":16,"text":17,"correct":18},"B","招标截止日",false,{"key":20,"text":21,"correct":18},"C","中标通知书发出",{"key":23,"text":24,"correct":18},"D","合同签订","对于实行招标的项目，一般以施工招标文件中规定的提交投标文件截止时间前的第 28 天作为基准日。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程计价","建筑工程",0]