[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-898354":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},898354,582,1,"单选题","关于合同价款调整，下列说法正确的有（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","当应予计算的实际工程量与招标工程量清单出现偏差（不包括因工程变更等原因导致的工程量偏差）超过15%时，对综合单价进行调整",false,{"key":16,"text":17,"correct":14},"B","发包人压缩的工期天数不得超过定额工期的25%",{"key":19,"text":20,"correct":21},"C","因为不可抗力造成承包人的施工机械设备损坏及停工损失，由承包人承担",true,{"key":23,"text":24,"correct":14},"D","任一计日工结束，已标价工程量清单中没有该类计日工单价的，由承包人提出，报发包人确认","A 错误，当应予计算的实际工程量与招标工程量清单出现偏差（包括因工程变更等原因导致的工程量偏差）超过 15%时，对综合单价进行调整；B 错，发包人压缩的工期天数不得超过定额工期的 20%；D 错误，任一计日工项目实施结束，已标价工程量清单中没有该类计日工单价的，由发承包双方按工程变更的有关的规定商定计日工单价计算。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程计价","建筑工程",0]