[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-898353":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},898353,582,1,"单选题","某分项工程招标工程量清单数量为4000m2，施工中由于设计变更调减为3000m2，该项目招标控制价综合单价为600 元\u002Fm2，投标报价为450 元\u002Fm2。合同约定实际工程量与招标工程量偏差超过±15%时，综合单价以招标控制价为基础调整。若承包人报价浮动率为10%，该分项工程费结算价为（ ）万元。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","137.70",true,{"key":16,"text":17,"correct":18},"B","155.25",false,{"key":20,"text":21,"correct":18},"C","186.30",{"key":23,"text":24,"correct":18},"D","207.00","(1)3000÷4000=75%，工程量减少超过15%，单价应调高（或不调）， (2)P2×（1－L）×（1－15%）=600×（1－10%）×（1－15%）=459 万元, (3)450\u003C459，P1按照459 调整,该分项工程费结算价=459 元\u002Fm2 ×3000m2=137.7 万元.",{"id":6,"name":27,"category":28,"favorite":29},"建设工程计价","建筑工程",0]