[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-898351":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},898351,582,1,"单选题","根据《建设项目工程总承包合同示范文本（实行）》（GF-2011-0216），下列变更事项，属于采购变更的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","对设备规格和数量的调整",false,{"key":16,"text":17,"correct":18},"B","改变检查、检验、检测、试验地点",true,{"key":20,"text":21,"correct":14},"C","重新进行竣工验收",{"key":23,"text":24,"correct":14},"D","对配套工程系统的工艺调整","A、D 是设计变更；C 是施工变更。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程计价","建筑工程",0]