[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-898350":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},898350,582,1,"单选题","关于工程总承包合同价款的结算，下列说法不正确的有（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","合同约定按月工程进度申请付款和付款时，发包人在收到承包人提交的每月付款申请报告之日起的14天内审查并支付",true,{"key":16,"text":17,"correct":18},"B","发包人延误支付进度款15 天以上，承包人有权向发包人发出要求付款的通知",false,{"key":20,"text":21,"correct":18},"C","发包人延误支付进度款达60 天以上，并影响工程实施的，承包人有权解除合同",{"key":23,"text":24,"correct":18},"D","发包人应在收到承包人提交的最终竣工结算资料后30 日内，结清竣工结算的款项","选项 A 错误，合同约定按月工程进度申请付款和付款时，发包人在收到承包人提交的每月付款申请报告之日起的 25 天内审查并支付。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程计价","建筑工程",0]