[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-898346":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},898346,582,1,"单选题","根据《建设工程工程量清单计价规范》(GB50500-2013)，关于工程预付款的支付和扣回，下列说法中正确的是（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","预付款的比例原则上不低于合同金额的10%，不高于合同金额的20%",false,{"key":16,"text":17,"correct":14},"B","承发包双方签订合同后，发包人最晚应在开工日期前14 天内支付预付款",{"key":19,"text":20,"correct":14},"C","在发出要求预付通知的14 天后，承包人仍未收到预付款时，可以停止施工",{"key":22,"text":23,"correct":24},"D","发包人应在预付款扣完后14 天内一次将全额预付款保函退还给承包人",true,"预付款担保也可以采用发承包双方约定的其他形式，如由担保公司提供担保，或采取抵押等担保形式。承包人的预付款保函的担保金额根据预付款扣回的数额相应递减，但在预付款全部扣回之前一直保持有效。发包人应在预付款扣完后的 14 天内将预付款保函退还给承包人。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程计价","建筑工程",0]