[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-898342":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},898342,582,1,"单选题","关于施工合同履行期间的期中支付，下列说法中正确的是（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","双方对工程计量结果的争议，不影响发包人对已完工工程的期中支付",false,{"key":16,"text":17,"correct":14},"B","对已签发支付证书中的计算错误，发包人不得再予修正",{"key":19,"text":20,"correct":21},"C","进度款支付申请中应包括累计已完成的合同价款",true,{"key":23,"text":24,"correct":14},"D","本周期实际支付的合同额为本期完成的合同价款合计","支付申请包括本期应支付的合同款，对已签发的任何支付证书有错误，发包人有权修正。若发承包双方对有的清单项目的计量结果出现争议，发包人应对无争议部分的工程计量结果向承包人出具进度款支付证书。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程计价","建筑工程",0]