[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-898341":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},898341,582,1,"单选题","施工合同履行期间，下列不属于工程计量范围的是（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","工程变更修改的工程量清单内容",false,{"key":16,"text":17,"correct":14},"B","合同文件中规定的各种费用支付项目",{"key":19,"text":20,"correct":14},"C","暂列金额中的专业工程",{"key":22,"text":23,"correct":24},"D","擅自超出施工图纸施工的工程",true,"工程计量的范围包括：工程量清单及工程变更所修订的工程量清单的内容；合同文件中规定的各种费用支付项目，如费用索赔、各种预付款、价格调整、违约金等。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程计价","建筑工程",0]