[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-898335":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},898335,582,1,"单选题","工程总承包企业投标报价决策时应准确估计成本:其成本费用应由（ ）等组成。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","勘察设计费用、采购费用、施工费用、总部管理费",false,{"key":16,"text":17,"correct":14},"B","勘察设计费用、分包合同费用、施工费用、利润",{"key":19,"text":20,"correct":21},"C","公司本部费用、施工费用、直接设备材料费用、分包合同费用",true,{"key":23,"text":24,"correct":14},"D","公司本部费用、施工费用、直接设备材料费用、风险费用","工程总承包项目的成本费用由施工费用，直接设备材料费用，分包合同费用，公司本部费用，调试、开车服务费用和其他费用组成，也可以将工程总承包费用按阶段分解成勘察设计费用、采购费用和施工费用三部分。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程计价","建筑工程",0]