[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-898331":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},898331,582,1,"单选题","关于合同价款与合同类型，下列说法正确的是（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","中标人应当自中标通知书收到之日起30 天内与招标人订立书面合同",false,{"key":16,"text":17,"correct":14},"B","工期特别近、技术特别复杂的项目应采用总价合同",{"key":19,"text":20,"correct":14},"C","实行工程量清单计价的工程，应采用单价合同",{"key":22,"text":23,"correct":24},"D","工程总承包招标的投标有效期为120 天",true,"招标人和中标人应当在投标有效期内并在自中标通知书发出之日起 30 天内，按照招标文件和中标人的投标文件订立书面合同。紧急抢险、救灾以及施工技术特别复杂的建设工程，发承包双方可以采用成本加酬金方式确定合同价款。实行工程量清单计价的建筑工程，鼓励发承包双方采用单价方式确定合同价款。@##",{"id":6,"name":27,"category":28,"favorite":29},"建设工程计价","建筑工程",0]