[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-898306":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},898306,582,1,"单选题","当初步设计深度较深、有详细的设备清单时，最能精确地编制设备安装工程概算的方法是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","预算单价法",true,{"key":16,"text":17,"correct":18},"B","扩大单价法",false,{"key":20,"text":21,"correct":18},"C","设备价值百分比法",{"key":23,"text":24,"correct":18},"D","综合吨位指标法","单位设备安装工程的概算编制办法包括预算单价法、扩大单价法、设备百分比法和综合吨位指标法，其中预算单价法适用于初步设计较深、有详细设备清单时。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程计价","建筑工程",0]