[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-898303":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},898303,582,1,"单选题","某地拟建一幢建筑面积为 2500m2 办公楼。已知建筑面积为 2700m2 的类似工程预算成本为 216 万元，其人、材、机、企业管理费占预算成本的比重分别为 20%、50%、10%、20%。拟建工程和类似工程地区的人工费、材料费、施工机具使用费、企业管理费之间的差异系数分别是 1.1、1.2、1.3、1.15，综合费率为 4%，则利用类似工程预算法编制该拟建工程概算造价为（ ）万元。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","245.44",true,{"key":16,"text":17,"correct":18},"B","252.2",false,{"key":20,"text":21,"correct":18},"C","287.4",{"key":23,"text":24,"correct":18},"D","302.8","综合调整系数=20%×1.1+50%×1.2+10%×1.3+20%×1.15=1.18，拟建工程概算造价=（216\u002F2700）×1.18 ×（1+4%）×2500=245.44（万元）。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程计价","建筑工程",0]