[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-898292":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},898292,582,1,"单选题","完成某单位分部分项工程需要基本用工4.2 工日，超运距用工0.3 工日，辅助用工1 工日，人工幅度差系数为10%，则该单位分部分项工程预算定额人工消耗量为（ ）工日。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","5.92",false,{"key":16,"text":17,"correct":14},"B","5.95",{"key":19,"text":20,"correct":14},"C","6.02",{"key":22,"text":23,"correct":24},"D","6.05",true,"",{"id":6,"name":27,"category":28,"favorite":29},"建设工程计价","建筑工程",0]