[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-898290":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},898290,582,1,"单选题","正常施工条件下，完成单位合格建筑产品所需某材料的不可避免损耗量为1.70kg，已知该材料的损耗率为6.30%，则所需这种材料的总消耗量为（ ）kg。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","28.28",false,{"key":16,"text":17,"correct":18},"B","28.68",true,{"key":20,"text":21,"correct":14},"C","28.25",{"key":23,"text":24,"correct":14},"D","27.27","1.70\u002F 6.30%+1.70=28.68kg。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程计价","建筑工程",0]