[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-898284":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},898284,582,1,"单选题","通过计时观察，完成某工程的基本工时为7h\u002F m3，辅助工作时间为工序作业时间的8%，规范时间占工作时间的13%，则完成该工程的时间定额是（ ）工日\u002F m3。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","1.03",false,{"key":16,"text":17,"correct":14},"B","1.04",{"key":19,"text":20,"correct":14},"C","0.98",{"key":22,"text":23,"correct":24},"D","1.09",true,"7\u002F8\u002F（1-8%）\u002F（1-13%）=1.09 工日\u002F m3。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程计价","建筑工程",0]