[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-898282":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},898282,582,1,"单选题","在工人的工作时间消耗中，属于有效工作时间且和工作量大小有关的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","辅助工作时间",true,{"key":16,"text":17,"correct":18},"B","准备与结束工作时间",false,{"key":20,"text":21,"correct":18},"C","休息时间",{"key":23,"text":24,"correct":18},"D","不可避免的中断时间","B 选项准备与结束工作时间的长短与所担负的工作量的大小无关，与工作内容有关。CD 选项属于必须消耗的时间，但是不属于有效工作时间。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程计价","建筑工程",0]