[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-898279":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},898279,582,1,"单选题","招标工程量清单应以（ ）为单位编制。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","建设项目",false,{"key":16,"text":17,"correct":18},"B","单位工程",true,{"key":20,"text":21,"correct":14},"C","分部工程",{"key":23,"text":24,"correct":14},"D","分项工程","招标工程量清单应以单位（项）工程为单位编制。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程计价","建筑工程",0]