[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-898277":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},898277,582,1,"单选题","在工程量清单中，最能体现分部分项工程项目自身价值本质的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","项目特征",true,{"key":16,"text":17,"correct":18},"B","项目编码",false,{"key":20,"text":21,"correct":18},"C","项目名称",{"key":23,"text":24,"correct":18},"D","项目计量单位","项目特征是构成分部分项工程项目、措施项目自身价值的本质特征。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程计价","建筑工程",0]