[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-898270":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},898270,582,1,"单选题","在编制工程量清单时，主要的步骤包括有①招标文件②编制工程量清单③计算工程量④确定项目特征⑤确定项目编码⑥确定项目名称⑦确定计量单位，下列排列顺序正确的是（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","①③④⑤⑥⑦②",false,{"key":16,"text":17,"correct":14},"B","①③⑥⑤④⑦②",{"key":19,"text":20,"correct":21},"C","①⑥⑤④⑦③②",true,{"key":23,"text":24,"correct":14},"D","①⑦⑥⑤④③②","工程量清单的编制程序：①招标文件；②确定项目名称；③确定项目编码；④确定项目特征；⑤确定计量单位；⑥计算工程量；⑦编制工程量清单。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程计价","建筑工程",0]