[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-898265":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},898265,582,1,"单选题","采用工程总承包方式发包的工程，其工程总承包管理费应从（ ）中支出。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","建设管理费",true,{"key":16,"text":17,"correct":18},"B","建设单位管理费",false,{"key":20,"text":21,"correct":18},"C","建筑安装工程费",{"key":23,"text":24,"correct":18},"D","基本预备费","建设管理费包括建设单位管理费、工程监理费和工程总承包管理费。①建设单位管理费：指建设单位发生的管理性质的开支。②工程监理费 指建设单位委托工程监理单位实施工程监理的费用。③工程总承包管理费：如建设管理采用总承包方式，其总承包管理费由建设单位与总承包单位根据工作范围在合同中商定，从建设管理费中支出。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程计价","建筑工程",0]