[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-898263":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},898263,582,1,"单选题","关于各应计量措施费的计算以下表述中正确的是（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","混凝土模板及支架费通常是按照模板面积以“m2”计算",false,{"key":16,"text":17,"correct":14},"B","排水、降水费通常按照排、降水日历天数按“天”计算",{"key":19,"text":20,"correct":14},"C","超高施工增加费通常按照建筑面积按“m2”计算",{"key":22,"text":23,"correct":24},"D","脚手架费可按照建筑面积“m2”计算",true,"A 混凝土模板及支架费通常是按照模板与现浇混凝土构件的接触面积以“m2”计算；B 排水、降水费分两个不同的独立部分计算，成井费按照你钻孔深度按“m”，排水、降水通常按照排、降水日历天数按“昼夜”计算；C 超高施工增加费通常按照建筑物超高部分的建筑面积按“m2”计算。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程计价","建筑工程",0]