[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-898254":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},898254,582,1,"单选题","为完成工程项目并达到使用要求或生产条件，在建设期内预计或实际投入的全部费用总和为（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","建设项目总投资",true,{"key":16,"text":17,"correct":18},"B","固定资产投资",false,{"key":20,"text":21,"correct":18},"C","建设投资",{"key":23,"text":24,"correct":18},"D","工程费用","B:工程造价（固定资产投资）：在建设期预计或实际支出的建设费用 C:建设投资：为完成工程项目建设，在建设期内投入且形成现金流出的全部费用；D:工程费用：建设期内直接用于工程建造、设备购置及安装的建设投资，可以分为建筑安装工程费和设备及工器具购置费。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程计价","建筑工程",0]