[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-898252":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},898252,582,1,"单选题","根据世界银行对建设工程造价构成的规定，只能作为一种储备可能不动用的费用是（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","未明确项目准备金",false,{"key":16,"text":17,"correct":14},"B","基本预备费",{"key":19,"text":20,"correct":21},"C","不可预见准备金",true,{"key":23,"text":24,"correct":14},"D","建设成本上升费用","未明确项目的准备金，用于在估算时不可能明确的潜在项目，这些项目是必须完成的，或它们的费用是必定要发生的。不可预见准备金只是一种储备，可能不动用。建设成本上升费用于补偿直至工程结束时的未知价格增长。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程计价","建筑工程",0]